What criteria must be observed for the association for own consumption?

  • A ZEV shares a single connection to the public power grid.
  • Objects adjacent to plots may be combined to form a ZEV. All but one grid connection must be removed.
  • The installed output of the photovoltaic system (kWp DC output) is at least 10% of the installed connection output of the ZEV to the power grid.
  • The supply between the participants is via private lines, no use of the public grid.
  • The solar power must be produced on the same or an adjacent plot and must be located behind the same grid connection point.
  • A ZEV always starts at the beginning of each month.
  • The formation of a ZEV must be requested from the grid operator at least three months in advance.

More information can be found here.